    I'm hoping someone out there has some ideas that can help me. For years, I have struggled with how to keep up with the workload of my employees to make sure that we do not fall behind on tasks. Our job involves working with up to six different Project Managers on as many as 15 different projects, each with their own independent timelines, customers, and Microsoft Project schedules (hint - Contract Pharmaceutical Manufacturing).

    Trying to keep abreast of all those schedules during the Weekly Review drives me crazy! The PM's do not talk to each other or try to integrate their schedules into some sort of Master Schedule. I'm looking for something simple of my own that pulls from those schedules into one for my own use - but don't want to spend hours each week struggling with Microsoft project.

    The other great thing is that our company does not allow us to install any special software outside the corporate standard, so I'm tied to the standard Microsoft Office suite.

    Any ideas anyone has would be greatly appreciated!

  2. #2
    Join Date
    Oct 2003
    Location
    Warszawa, Poland
    Posts
    3,159

    Question Why do you need to synchronize these schedules?

    Why do you need to synchronize these schedules?
    TesTeq - Follow me on Twitter - BIZNES BEZ STRESU (blog in Polish)

  3. #3
    Join Date
    Jan 2006
    Location
    Moscow, Russia
    Posts
    624

    Default

    Would you like to track the projects your PMs are doing?

  4. #4
    Join Date
    Oct 2003
    Posts
    328

    Default

    Quote Originally Posted by Nitengayle View Post
    I'm hoping someone out there has some ideas that can help me. For years, I have struggled with how to keep up with the workload of my employees to make sure that we do not fall behind on tasks. Our job involves working with up to six different Project Managers on as many as 15 different projects, each with their own independent timelines, customers, and Microsoft Project schedules (hint - Contract Pharmaceutical Manufacturing).

    Trying to keep abreast of all those schedules during the Weekly Review drives me crazy! The PM's do not talk to each other or try to integrate their schedules into some sort of Master Schedule. I'm looking for something simple of my own that pulls from those schedules into one for my own use - but don't want to spend hours each week struggling with Microsoft project.

    The other great thing is that our company does not allow us to install any special software outside the corporate standard, so I'm tied to the standard Microsoft Office suite.

    Any ideas anyone has would be greatly appreciated!
    Since you stress your desire to integrate timelines into a Master Schedule, I do think it would be worth the overhead to learn MS Project. It really is the tool you need. It's often a struggle to learn new stuff, but you are managing PMs and 15 concurrent projects. You need a sophisticated tool that can handle the complexity of your job.

    If you merely want to track the status of multiple projects, you can use MS Outlook. You should make liberal use of the Contacts field in Outlook Tasks. This way you can create your own views that allow you to filter by Contact. You will enter the PM's name in the Contact field.

  5. #5

    Default

    Everyone,
    I need to synchorize the schedules so that I have a good overview of when things are due that my people are responsible for. Our work involves creation of documents that have to be routed and approved before they can be executed, so the prep work needs to start in advance of when the task is actually due. Right now most of it is in my head, and I want it out!

    Moises,
    I am fairly proficient with the basics of projects, but is there a way to copy out of multiple schedules into one without recreating all the predecessors? The contacts approach might work best for me, but with the project as the Contact. Right now I have configured my Outlook to the "Total Daily Control" model, a variation of the GTD approach.

  6. #6
    Join Date
    Oct 2003
    Posts
    328

    Default

    First, I would think that the Gantt chart capabilities of MS Project would be of great use to use. For any date, you could view your status with respect to multiple deadlines.

    If you don't want to spend all that time keeping MS Project up to date, then why not make heavy use of your calendar, and maybe a tickler file? If Document Y is due in 3 weeks for Project X from Manager Z, put that in your calendar one week before it's due.

  7. #7

    Default

    Alternatively...

    How about a really big sheet of paper, or a big whiteboard? Chart it out on that. Once it's all worked out, you can print it up nicely and hang it in your cube or what-have-you.

    I've been thinking about documentation like this recently. I may be wrong, but I think a lot of folks get the wrong idea about schedules and specs and designs. They think that those things should be updated all the time. In my opinion, they should be rewritten frequently.

    Real life tends to snarl up schedules and designs. I've found that at some point, your spec or schedule gets hopelessly out-of-date. Folks struggle to fix these documents, when it would take less effort to create a new, clean one.

    So, why not take a little time to create a new schedule, knowing that it won't stay perfect? You'll be able to tweak it as time goes on, of course. But I think we'd all experience fewer headaches if we let go of trying to make our documentation exactly match reality at all times.

    And there I go, reading the tea leaves on a simple question....

  8. #8

    Default Reading the Tea Leaves!

    Brent,
    You're right - I think that's part of my frustration with Project, as soon as the project schedule is created, it's obsolete. The board is a good idea through, I have one with movable magnets on it that would cover an entire year. Thanks!

+ Reply to Thread

Similar Threads

  1. DA staff clarification on next actions needed
    By Anonymous in forum PUBLIC: Discuss Getting Things Done
    Replies: 10
    Last Post: 02-25-2003, 08:57 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts